HOME  >  Precast Concrete Division  >  Area of Application

Area of Application

 
Engineering Method Summary
Staircase can simply made with Precast Concrete. The method is divided into two methods.

  1) Floor by Floor Method: Precast concrete staircase and in-site concrete wall panel are
assembled and placed simultaneously per floor
  2) Part by Part Method: Place in-site concrete wall panel of all floor first, and assemble
precast concrete stairways for every floor at once. These methods drastically
improve construction quality as well as safety during construction as unskilled
workers can simply complete the construction of complicate staircases, which skilled
workers are required.
Advantages
Continuous construction of staircase is available by using system form
Staircase wall panel is also available in PC.
Improved quality of staircase
Floor by Flood Method
  • Method (A)
    - The engineering method
      developed for simultaneous
      construction for each floor
    - Left and right wall panels,
      landing space slabs are also
      available in precast method.
      With precast concrete staircase,
      Full stair area is available in PC
  • Method (B)
    - Instead of using full precast
      wall panels for left and right in
      method (A), the method (B) uses
      half PC wall panels.
  • Method (C)
    - Only staircase and landing
      space are made in precast and
      every walls of staircase is made
      with half PC slab.
     
    Construction Process
    • Arranging iron bars in
      outer mold
    • Inner PC form panel
      installing
    • Lower floor PC stairs
      and landing space
      installing
        • Upper floor half PC
          slab installing
        • Upper floor PC stair
          installing
        • Arranging iron bar on
          the top and placing
          concrete
       
      Detail Drawing
      • PC Stair + Upper Landing Space
      • PC Stair + RC Wall
      • PC Stair + Lower Landing Space